Discovery forces delay on new Lancefield Kinder/MCH build
Last updated on 24 April 2024
*Please note: This item was updated on 3 May 2024 with some minor tweaks to the copy and quotes, due to the original being published in error. This does not substantially change the update.
Project timelines for the new kindergarten and Maternal and Child Health Centre in Lancefield have changed following the discovery of a cultural artefact during site preparation works.
In line with strict protocols around such unexpected discoveries, works were immediately paused. The Victorian School Building Authority (VSBA) has consulted with the relevant Traditional Owner Corporation and a heritage consultant has been engaged to prepare a Cultural Heritage Management Plan (CHMP) for the site so that works can progress.
“The new kinder and Maternal and Child Health Centre has been delayed, as a result of the discovery of a cultural artefact,” said Council’s Director Community, Maria Weiss.
“We will continue to work closely with the VSBA and keep families and the broader public updated as the project progresses. This will include sharing revised project timelines when they are available.”
The project, located next to Lancefield Primary School, will feature a modern three-room facility which is largely built offsite through modular construction.
For more information about the construction works, residents can contact the VSBA on 1800 896 950, email vsba@education.vic.gov.au or visit the VSBA’s project page online.